Engineering Challenges

Construction of the SWP was truly an engineering marvel. The Project crosses more than 600 miles of terrain, both mountainous and flatland. A water project of its magnitude had never been attempted before. A new, young generation of engineers, fresh out of college, was recruited to help the more seasoned staff tackle the challenges that lay ahead. The following is a sampling of these engineering accomplishments.

Lake Oroville, the SWP’s largest reservoir with a power plant, built in a cavern excavated under the dam, is impressive in its scope. Its earthfill dam stands 770 feet tall, the tallest in the nation, with a crest (top of the dam) 6,920 feet long. More than 80 million cubic yards of material were needed to build Oroville Dam—enough material to build a two-lane highway around the earth.

California Aqueduct
Engineers decided to build the earthfill embankment with materials readily available at the site. This feat required huge tools like a bucketwheel excavator with eight-1.8 cubic yard buckets. The excavator could scoop up rocks within its 30-foot path and unload the rocks onto a conveyor belt about three miles long. The belt moved the rocks into a system that fed 10 hoppers at a loading station. At the station, the hoppers loaded trains of 40 gondolas, pulled by double diesel electric locomotives.

The trains, loaded in 15 minutes, travelled some 12 miles to the gondola dumper, where the loaded gondolas were disconnected from the train and the engine moved into place to pick up an empty string of cars for a return trip. The dumper could seize two fully loaded gondolas at a time and turn them upside down, dumping their 220-ton load of rocks onto a half-mile conveyor belt that crossed the Feather River to a stockpile near the dam. Running 24 hours a day with the three pairs of locomotives, 45-50 trains were dumped every 24 hours, producing nearly 500,000 cubic yards of material each week.

Hyatt Powerplant is located underneath the dam and lake. Its chamber was blasted from a metavolcanic rock formation and is large enough to hold almost two football fields. Miners drilled holes, loaded them with explosives, and blasted away the rock. Rock bolts or “structural steel framing” were used to hold the newly exposed rock. The bolts were anchored in place by an expansion anchor, tensioned to a specified stress, packed and sealed at the rock face, and finally grouted.

Another major challenge was the building of the California Aqueduct. Much of the aqueduct parallels the San Andres Fault Zone and crosses other major faults. More than 100 potential alignments were studied, and evaluations considered the seismic hazards the faults presented. Where the alignment crosses active faults, canal sections or pipelines are located near or at ground level to facilitate quick repair. Automatically controlled check gates were also installed upstream of these crossings to shut off flows if an earthquake ruptured the canal.

Also, approximately 200 miles of the aqueduct were to cross the westside of the San Joaquin Valley, where unconsolidated soil deposits were known to be prone to shallow subsidence. Once saturated, settlement of these unconsolidated soils would damage the unreinforced concrete lining planned for use in constructing the aqueduct.

Field test ponds in subsidence-prone areas produced as much as nine feet of subsidence. To solve this problem, hundreds of water-filled preconsolidation ponds were constructed along the alignment of the aqueduct to ensure that settlement occurred before canal construction. The ponds were kept filled for as long as six months.

The Tehachapi Crossing presented another test of engineering ingenuity because the crossing would traverse or parallel several major faults including San Andreas, Pastoria, Garlock, and White Wolf. The simpler and more direct way would have been to drill a single tunnel at a lower elevation. But what if an earthquake struck, damaging the tunnel? It could take several months to reach the damaged areas and would leave Southern California without SWP water.

So engineers had four tunnels drilled at a higher elevation, near the top of the mountain range. The tunnels are connected by siphons and pipes with access sites for inspections and repairs.